OpenAI says its future US data centres will cut power use when local grids are under strain

Its planned campus in Effingham County, Georgia, where it agreed in July to give Georgia Power up to 1,000 megawatts of flexible demand, will be the programme's pilot.

By Nora Quinn · 3 Nov 2026 · 1 min

Its planned campus in Effingham County, Georgia, where it agreed in July to give Georgia Power up to 1,000 megawatts of flexible demand, will be the programme’s pilot.

OpenAI said on Monday that it will seek arrangements for its future US compute campuses to reduce their electricity use when local grids are under strain, under what it calls the Grid Protectors Program. Its planned campus in Effingham County, Georgia, will serve as a pilot. Under an agreement Georgia Power announced in July, OpenAI is expected to need about 3,200 megawatts there and has agreed to provide up to 1,000 megawatts of flexible demand response, reducing its use in times of high demand. OpenAI said its campuses may also supply power from on-site generation or storage and use batteries and power controls, depending on local needs, and that it has committed to pay the full infrastructure and electric-service costs of the Georgia project. The arrangements will differ by location, the company said.

Sources: OpenAI · Axios · Georgia Power (22 Jul)